Release Dates
Production: 6.26.2019
Cut-In Ticket Enhancement
Current functionality: When a transmission ticket is marked as cut-in, a Restoration Plan Update Request is created in Update Required status. Unchecking the cut-in
flag does not close the Restoration Plan Update Request.
Enhancement: If a cut-in transmission ticket is unchecked as cut-in and nothing has been done with the Restoration Plan Update Request, eDART will set its
status to Cancelled by Company.
See slide 27 of
June 2019 eDART User Group Meeting.
Reactive Reserve Check (RRC) Enhancements
Company Timestamp added to RRC Report and RRC Full download: Indicates the last time the RRC was updated from the company side either by ICCP, XML or web UI
RRC Full download now returns the open RRC or last posted RRC if no RRC ID is selected: Previously returned a system error
Refresh button removed from posted RRC reports: there is nothing to refresh on a posted report.
See slides 28-29 of
June 2019 eDART User Group Meeting.
TERM Ticket Enhancements
Equipment End filter added to View/Revise, History Report and Recently Restored filters. Filter page also re-arranged to accommodate new field.
See slide 30 of
June 2019 eDART User Group Meeting.
Voltage Schedules
Fixed issue with Voltage Schedule tickets not being flagged as Late if not acknowledged by Effective Date.
See slide 6 of
June 2019 eDART User Group Meeting.
Voltage Schedules
Daily emails will be sent out when the Annual Review for Voltage Schedules is in progress if acknowledgement has not been completed:
Email sent to the same email address currently receiving notifications.
Email text will include the posted message on the TO Annual Review and GO Annual Review pages.
Email text will include the posted message on the TO Annual Review and GO Annual Review pages.
Daily emails will be sent to the TO when each GO in TO’s transmission zone completes all acknowledgements for the Annual Review.
Current daily email to TO now excludes Needs Schedules tickets if there is another ticket in the queue for the unit.
Notifications will only be sent for units that actually require TO action.
Likewise, Voltage Schedules button will only be red if there are units that actually require TO action and will ignore Needs Schedules tickets for
units with another ticket in the queue.
See slides 31-32 of
June 2019 eDART User Group Meeting.
IRC Statistical Report
New report to track Generation company’s response to Instantaneous Reserve Checks (IRCs) per month:
Report also available to PJM Dispatch.
Displays information on available capacity , total units, total reserves acknowledged, total reserves unacknowledged and score.
Score = (Total Reserves Acknowledged / Total Reserves) x 100
See slides 23-24 of June 2019 eDART User Group Meeting.
General
Updated phone number for the PJM Support Center for locked accounts.
See slide 6 of
June 2019 eDART User Group Meeting.